Friday, September 4, 2015

Step attach angle install

The step attach angles were installed along with the bulkhead. Instructions state that the steps can be added at any time during the install, so I have elected to wait until later in the build.  Bushings were placed.

Time: 1 hr.

Riveting step attach angles

Riveting bulkhead

Interior view after riveting step attach angles.



Thursday, September 3, 2015

Step angle bracket / step floor nutplate a

 Worked today on the step attach angles. It involved cutting and match drilling the step attach angles and leveling the step to match drill the hole for the step.  The angles required priming, so while the primer was setting I moved forward and attached nutplate to the step floor and the baggage bulkhead.

Time: 1.5 hrs

Match drilling step attach angles.

Match drilling step hole

Priming step attach angles

Nutplates on Step floor

Nutplates on step floor

Nutplates on baggage bulkhead






Wednesday, September 2, 2015

Finish bottom skin

Bottom skin was completed today. Lots of rivets.  The stiffeners and doublers were placed while riveting the bottom skin. The step attach angles and nutplate brackets were then cut and prepared. Nut plates were attached to the brackets.

Time: 2.75 hrs.

Bottom skin clecoed

Bottom skin riveted

Step attach angles and nutplate brackets



Monday, August 31, 2015

Start bottom skin

Not much time to work today, but did squeeze a little time to attach the nutplate to the access holes on the bottom skins and start clecoing the bottom skin in place.

Time: 0.75 hrs.

Nutplates added to bottom skin

Start of clecoing bottom skin to fuselage


Saturday, August 29, 2015

Control column / step ribs / corner skins

Got some help today from my wonderful oldest two children.   We started by added nutplates to the seat floor flange.  My children then carefully placed and bolted the control column as per plans.  Step ribs were then riveted in place. and bushings placed in the fuselage as per plans.  Care taken into getting the right bushing in the right hole.  The corner skins were then prepared and riveted to the fuselage.  I finished the day by preparing the bottom stiffeners and doublers. Great work happens with many hands.

Time: 2.25 hrs.

Nutplates attached to seat rib flange

Current look of fuselage

Control column bolted in place

Step ribs

Bushings added

Corner skins placed

Bottom stiffeners and doublers prepared







Wednesday, August 26, 2015

Bulkhead

Lots accomplished today. Started by drilling out the holes in the bulkhead as per plans. The bulkhead flange was then riveted. The stub spar receptacles were fitted to the spar and then riveted in place.  Doublers and control column assemblies were then added to the bulkhead.  Nut plates were added to the bulkhead. The bulkhead was riveted to the sseat ribs and the seat ramp floors were placed.


Time: 3.5 hrs.

Bulkhead flange riveted

Bulkhead doubler riveted

Control column assembly and stub spar receptacle

Lots of nutplates

Bulkhead doubler

Bulkhead assembly riveted to the sear ribs.

Seat Ramps







Tuesday, August 25, 2015

Control column mount assembly / stub spar support

The past month has been busy with spending time on 2 big boy scout adventures with my son and other family duties. There is always something to do outside while the weather is good. So it makes it hard to keep the plane project moving, but now I am back at it and it feels good. My goal is to get the fuselage completed by the end of the year. We will see if that will be accomplished.

Today I spent a small amount of time getting the parts of the control column mount assemblies prepared and parts riveted together. The bulkhead flanges and stub spar receptacle supports were then prepared.

Time: 1 hr.

Control column mount assembly

Bulkhead flanges / Stub spar receptacle support