Time: 1.25 hrs.
This is a log of the build of a Vans RV-12, kit #120895. This will be my first experience in aircraft construction and I hope to learn a lot along the way.
Showing posts with label Section 39 - Autopilot bracket. Show all posts
Showing posts with label Section 39 - Autopilot bracket. Show all posts
Monday, September 7, 2015
Step floor / baggage bulkhead.
Had the help of B today. We riveted the step floor and baggage bulkhead. During these steps part of the autopilot brackets were installed.
Time: 1.25 hrs.
Time: 1.25 hrs.
Tuesday, July 28, 2015
Seat rib assemblies continued
Started today by preparing the flaperon stops and riveting one flaperon stop and pulley assembly to the seat ribs. The other flaperon stop and the flaperon mixer were then riveted to the other seat ribs. During this time also the auto pilot bracket was installed as per plans.
The crotch strap brackets were then prepared and then riveted to the seat ribs.
Time: 2.25 hrs
The crotch strap brackets were then prepared and then riveted to the seat ribs.
Time: 2.25 hrs